Status Report 5

Team: Alex Goldyuk, Amine Hocine, Alexander Lewoczko, Lexi Reicks, Ryan Toepfer, Armando Vila

Report Date: 12/2/2019

Project: Wireless Backyard Chicken Coop

Project Status: In-Progress


Deliverables:

DELIVERABLE Status ETA
Identify Project Hardware/Software Requirements Completed 4/2/20
Holistic Design Completed 12/2/2019
Accurate Prototype Sensor Readings In-Progress 12/25/2019
Web Application Skeleton Completed 11/25/2019
All Systems Connected In-Progress 12/25/2019
Complete System Implementation In-Progress 01/28/2019

Overview:

Since the last report we have completed our final version of the design document. As well we have recieved almost all the required hardware and will be attempting to create our first prototype by the end of dead-week.

Current Accomplishments:

Nearby Milestones: