Team: Alex Goldyuk, Amine Hocine, Alexander Lewoczko, Lexi Reicks, Ryan Toepfer, Armando Vila
Report Date: 12/2/2019
Project: Wireless Backyard Chicken Coop
Project Status: In-Progress
Deliverables:
DELIVERABLE | Status | ETA |
---|---|---|
Identify Project Hardware/Software Requirements | Completed | 4/2/20 |
Holistic Design | Completed | 12/2/2019 |
Accurate Prototype Sensor Readings | In-Progress | 12/25/2019 |
Web Application Skeleton | Completed | 11/25/2019 |
All Systems Connected | In-Progress | 12/25/2019 |
Complete System Implementation | In-Progress | 01/28/2019 |
Overview:
Since the last report we have completed our final version of the design document. As well we have recieved almost all the required hardware and will be attempting to create our first prototype by the end of dead-week.
Current Accomplishments:
Nearby Milestones: